Page 33 - Freshwater-Biology-and-Ecology-Handbook
P. 33

Table 1.2
            Water Framework Directive timetable (adapted from Foundation for Water Research). Colour coding indicates the time
            allowed for each activity.

             Complete                                                           EU
             action by   Action Required                                        Directive   Overview
             year end                                                           Articles
                                                                                Article 22
               2000    Water Framework Directive entered into force
                                                                                Article 25
                                                                                           3 years for Member
                       •  Transpose requirements to national legislation        Article 23  States to prepare
               2003
                       •  Define River Basin Districts and Authorities          Article 3

               2004    Characterise river basins: pressures, impact and economic analysis  Article 5
               2005    •  Identify significant trends in groundwater pollution  Article 17

                       •  Establish environmental monitoring programmes         Article 8
                       •  Publish and consult on a work programme for the production of the first
               2006     River Basin Management Plans (RBMPs)                    Article 14

                       •  Establish environmental quality standards (EQSs) for surface waters  Article 16  6 years to analyse
                                                                                           issues and prepare
                       •  Report monitoring programmes to the EC                           the River Basin
               2007    •  Publish and consult on summary of Significant Water Management   Article 14  Management Plans
                         Issues (SWMI) for each River Basin District

               2008    Publish and consult on drafts of the RBMPs               Article 14
                       •  Publish the first RBMP for each River Basin District  Article 13
               2009    •  Establish programmes of measures (PoMs), in each River Basin
                         District in order to deliver environmental objectives  Article 11
                       •  Report RBMPs, including PoMs, to the EC               Article 9
               2010
                       •  Introduce water pricing policies                                 3 years to put
                                                                                           Programmes of
                       •  Ensure all POMs are fully operational                 Article 11  Measures in place
               2012
                       •  Report progress in implementing the first RBMPs       Article 15

               2013    •  Review progress of the first RBMP cycle
                                                                                           3 years to achieve
                       •  First management cycle ends
               2015                                                                        specified objectives
                       •  Main environmental objectives specified in the first RBMPs met?  Article 4
                                                                                           Further 6 years
                       Second River Basin Management Plans (review and update first RBMPs)  Articles 13,   planning, consultation
               2015
                       and first Flood Risk Management Plans                    14 and 15  and implementation
                                                                                           cycles
                       Second management cycle ends
                                                                                           Further 6 years
               2021    •  Main environmental objectives specified in the second RBMPs met?  Article 4  planning, consultation
                                                                                           and implementation
                                                                                Articles 13,   cycles
                       •  Third management plans (review and update second RBMPs )
                                                                                14 and 15
                       Third management cycle ends
                                                                                           Further 6 years
                       •  Final deadline for environmental objectives           Article 4  planning, consultation
               2027
                       •  Main environmental objectives specified in the third RBMPs met?  Article 13,  and implementation
                                                                                           cycles
                                                                                14 and 15
                       •  Review and update third RBMPs

                                                                  Freshwater Biology and Ecology Handbook  |  33
                                                                                                                 –
   28   29   30   31   32   33   34   35   36   37   38